Truck-crane load-test and periodic inspection records

Check that every crane record identifies the unit, procedure and tested configuration. It should also state the instruments, conditions, findings, exceptions and return-to-service approval.

Identity, test scope and defect closure
  • 01Installed crane and chassis identities
  • 02Procedure, setup, instruments and findings
  • 03Repair, reinspection and release decision
View the reference imageTruck-crane load test with inspection records and measured lift conditions

Truck-crane load test with inspection records and measured lift conditions

Match the record to the crane and installation being accepted

An inspection result for a similar crane, an earlier installation or a different setup cannot automatically cover the delivered unit. Start with the chassis, crane model, serial number and installation identity.

Commissioning, periodic inspection, maintenance inspection and load testing can be different activities. Keep their scope and responsible qualified organization visible. A visual check cannot prove that a load test occurred, and a load test does not replace the operating chart.

Can the test be reconstructed from the report?

Check the crane serial number, carrier identity, load chart revision and rated-capacity configuration. Record the test weight, working radius, boom configuration and outrigger position used. Where measurements support the result, ask for instrument identities and applicable calibration certificates. A video supports the report only for the conditions it actually shows.

A proof-load test, stability test, commissioning inspection and periodic inspection answer different questions. Do not assume a test for one purpose satisfies another or select a universal test-load percentage from a generic buying guide. The competent person should identify the applicable procedure and the basis for the inspection certificate.

Keep findings and repairs with the inspection history

For lifting equipment inspection, retain wire rope and hook findings, visible hydraulic leaks, safety-device checks and any restrictions. Record the status of overload protection or the load moment indicator where fitted and included in the test scope. Keep a defect report traceable through the repair record to the repeat check.

Separate the buyer's release decision from the operator's lifting plan and ongoing daily inspection. Truck crane inspection intervals depend on the equipment, conditions and applicable regime. Keep the operator manual, inspection schedule and return-to-service decision with the truck; a previous pass is not continuing approval after damage, alteration or a new defect.

Read the method and findings before accepting a pass label

The dossier needs the procedure, acceptance criteria, setup, date, relevant instruments and conditions. Link each finding to repair, reinspection and approval so an open defect does not disappear behind a summary certificate.

Scroll horizontally to view all columns.

Read the method and findings before accepting a pass label
DecisionWhat to establishCondition or limit
IdentityMatch chassis, crane model, serial and installation.A model-level certificate is not a unit-level record.
ProcedureState governing method and acceptance criteria.A pass label without basis is not auditable.
ConditionRecord setup, configuration, load and environment as applicable.Results apply only within the stated test scope.
ClosureLink findings to repair, reinspection and approval.Open safety-critical exceptions prevent service.

Separate commissioning evidence from ongoing inspection

Record the scope of each inspection document before approving release. An installation check concerns the mounted system; a functional check concerns the tested controls or movements; a load-test record covers its stated conditions. None replaces the approved chart. OSHA distinguishes inspection circumstances, including work after modifications; use the applicable local requirements to determine the project obligations. OSHA 1926.1412: crane inspections OSHA 1926.1417: crane operation

Scroll horizontally to view all columns.

Crane handover record review
RecordRequired traceabilityAcceptance question
Installation and commissioningTruck and crane identity, installation revision and responsible partyDoes the record cover the configuration being delivered?
Load test, when requiredApproved method, crane/boom and attachment identity, radius, outrigger deployment, test load, instruments and resultDoes the record match a permitted load-chart configuration, with defects closed?
Transport loadingAs-installed mass, remaining cargo allowance and axle loads with the crane stowedIs the truck within both gross and axle limits for the planned delivery load?
Functional inspectionItems checked, findings, date and inspector identityDoes the report identify the controls and devices actually checked?
Repair or modificationWork scope, approvals, inspection and release statusHas the change been assessed before return to service?

OSHA 1926.1412: crane inspections

  • Reconcile identifiers across chart, nameplate and reports
  • Request missing pages, signatures or test conditions
  • Track each defect to a disposition and authorized closure
  • Keep the next inspection responsibility and applicable schedule in the handover package

This is a document-review framework. Keep the inspection scope and configuration with the findings, corrective work and authorized release decision.

Keep the release decision with the closed inspection findings

Request the applicable records for the installed crane and keep signed defect closures with the authorized release decision. Qualified organizations and local requirements determine the tests and inspections.

Information to prepare for this review
  • Truck, crane and installation identity
  • Required commissioning and periodic scope
  • Applicable procedure and authority basis
  • Test setup, load and instrument requirements
  • Inspection items and acceptance criteria
  • Exception, repair and return-to-service workflow
Records to request and keep
  • Unit and installation identity
  • Procedure, configuration and acceptance basis
  • Instrument and test-load traceability where applicable
  • Findings, corrective action and return-to-service approval
Common mistakes and what to check instead
  • Accepting a generic manufacturer certificate as a unit test: Match the evidence type to the required project scope.
  • Treating a load test as proof of every working radius: The approved load chart remains controlling.
  • Leaving inspection findings open: Require documented disposition and authorized closure.

Buyer questions and practical limits

Does a load-test certificate establish every lifting capacity?
  • Only the identified test scope and configuration are evidenced. The approved load chart and operating conditions still govern each planned lift.
Who should select the test load and method?
  • The competent party responsible for the test should select an applicable procedure using the equipment instructions and relevant requirements. This guide supplies no universal test percentage.

Scope of this guide

This guide provides no test load, proof-load percentage, test sequence or operating instruction.

Qualified organizations and applicable rules control testing and inspection.

Remove the crane from service for overdue required inspection, structural damage, failed safety systems or unresolved critical findings.

Sources and applicability

OSHA 1926.1417: crane operation

U.S. construction crane operating requirements and manufacturer procedures. Applicability depends on jurisdiction and activity; not a KEEYAK certification.

Sources checked:

OSHA 1926.1412: crane inspections

U.S. construction crane inspection scope, qualified inspection and records. Does not establish a universal export inspection interval or proof-load procedure.

Sources checked:

KEEYAK buying process

Explains the steps from describing the job and comparing quotations to configuration approval and inspection.

KEEYAK Truck-Mounted Crane family

Defines the relevant product family and published configuration boundaries. Project-specific ratings require the selected OEM documents.

OSHA 29 CFR 1910.180

Official U.S. reference supporting configuration-specific load charts, stability factors, inspection identity and removal of hazardous deficiencies. Local rules may differ.

Discuss the vehicle you need

Tell us what the vehicle will carry or do, where it will operate and the load you expect. Include any questions you need answered before choosing a configuration.

Discuss your requirements