Check transport loading and working support separately
The chassis carries the equipment on the road; the deployed support system handles working reactions at the site. Passing one condition does not establish the other. Use completed gross and axle mass for transport, with the actual stowed installation.
Working support needs the approved reactions for the boom, platform load and setup. Dividing total machine weight by four does not produce a valid outrigger reaction. Pad area alone also cannot resolve soil variability, voids or slope.
Before accepting a KV100-based offer, ask for the completed axle loads and deployed footprint of your proposed installation. The approved support reactions are needed too. The Russia order names the ISUZU KV100 and specifies an 18 m working height with a 200 kg basket capacity, but provides neither the axle loads nor the deployed footprint. KEEYAK Russia ISUZU KV100 aerial platform order record
Separate transport dimensions from operating space
Record transport width, stowed height, chassis wheelbase and rear overhang for access and parking. Then add the outrigger footprint, outrigger span, tail swing and space needed for the work. Traffic lane closure and separation from passing vehicles may affect where the aerial work platform truck chassis can stand.
Plot the work point within the offered working envelope using working height, horizontal outreach and basket capacity together. Ask whether partial outrigger extension is permitted and what envelope applies to that exact setup. A photograph showing retracted stabilisers is not an approval for restricted-width operation.
What ground information does the platform supplier need?
Ask for the specified stabiliser spread, maximum support reactions and outrigger pad requirements for assessment by the responsible site specialist. Ground bearing pressure depends on support load and effective support area; visual appearance cannot establish the capacity of a surface, buried structure or cover.
Include slope limit, chassis levelling, wind limit and underground services in the site survey. The safety interlock and tilt sensor support the equipment's defined controls; they do not replace ground assessment. Review platform load, gross vehicle weight and axle load with the manufacturer manual before accepting the combined chassis and aerial platform installation.
Reserve the whole working footprint
A truck that fits through a narrow street may lack space to deploy and work. Include outriggers, tail swing, platform movement and traffic exclusion. Support pads or a solid surface remain part of the required assessment, alongside the manufacturer and local conditions.
Hypothetical purchasing scenario: A compact truck fits the narrow street, but a boundary wall restricts the proposed parking space. Check the full working footprint and traffic clearance against the site drawing, with an engineering assessment of the ground using the approved support reactions. Change the parking position or vehicle proposal before ordering if a compliant setup cannot be shown.
Scroll horizontally to view all columns.
| Decision | What to establish | Condition or limit |
|---|---|---|
| Transport mass | Calculate completed gross and axle loads in stowed condition. | Bare chassis payload is not installed-equipment capacity. |
| Support reactions | Use the defined boom, load and setup reaction case. | Machine mass divided by four is not a valid outrigger reaction. |
| Ground support | Compare approved pad and ground capacity with support-reaction data reviewed by the responsible engineer. | Pad area alone does not address soil variability, voids or slope. |
| Site footprint | Reserve outrigger, tail-swing, platform and traffic exclusion space. | A stable setup is still unsuitable if the layout makes traffic movement unsafe. |
Request transport and support evidence for the proposed installation
Send the site envelope and known ground constraints with the task positions. Ask qualified engineering and site personnel to establish the reaction and ground-support basis. Leave setup approval open for unverified ground, insufficient footprint or uncontrolled traffic.
Information to prepare for this review
- Selected boom and platform system mass
- Chassis wheelbase, gross and axle ratings
- Subframe and installation requirements
- Outrigger geometry and reactions
- Ground condition, slope and pad method
- Traffic lane, obstacle and exclusion-space limits
Records to request and keep
- Completed-vehicle mass and axle calculation
- Approved installation and subframe documentation
- Outrigger reaction and footprint data
- Ground and work-zone setup assessment
Common mistakes and what to check instead
- Choosing the smallest chassis for access: Check installation, mass, axle, support and road requirements first.
- Estimating equal outrigger loads: Use the relevant manufacturer or qualified reaction data.
- Ignoring the road space needed for setup: Draw the full setup and exclusion envelope on the site plan.
Buyer questions and practical limits
Can an aerial platform work with one outrigger partly extended?
- Only if the exact machine and setup are approved for it, using the specified restricted working envelope and controls. Obtain model-specific instructions.
Can larger pads make any ground suitable?
- No. Pad sizing requires support reactions and ground assessment, including weak or buried structures. A larger pad does not establish the capacity of unknown ground.
Scope of this guide
This page does not design a subframe, pad or ground-support system.
Qualified engineering, manufacturer requirements and site assessment control setup.
Do not set up on unverified ground, excessive slope, inadequate footprint, uncontrolled traffic or unresolved support reactions.
Sources and applicability
Explains the steps from describing the job and comparing quotations to configuration approval and inspection.
Provides public checklists and worksheets; the signed project documents remain controlling.
Defines the relevant product family and published configuration boundaries. Project-specific ratings require the selected OEM documents.
Official U.S. reference supporting manufacturer load limits, controls, outriggers, brakes and travel checks. It is not a destination approval or KEEYAK rating.
Official U.S. guidance for worksite assessment, training, inspection, platform load, reach and stabilization. Local rules may differ.
This confirmed Russia order specifies an ISUZU KV100 aerial platform with an 18 m working height and a 200 kg basket capacity. It gives no completed axle loads or deployed dimensions, and no outrigger reactions or approved ground-support details. Delivery and site commissioning are not documented. The order record does not confirm the wheelbase.
US workplace guidance on pre-start inspections and defective equipment. It does not certify an offered truck or replace destination requirements.
Sources checked: